New York Jets/New York Giants, New Meadowlands MetLife Stadium, East Rutherford
New Jersey
Date: 2009, 2018, 2023
EAST RUTHERFORD, NJ–As the Meadowlands prepared itself for its biggest day in football—Superbowl XLVIII—one thing was certain—the stadium expansion joints were ready.
In the same way that the Meadowlands ushered in the era of billion-dollar stadiums, it also marked a watershed in the structural expansion joint industry. With seismic stadium expansion joints 10-inches (250mm) wide, and a design requirement that they be watertight at the deck surface, through all direction and plane changes, between different deck and wall technologies, and capable of handling rolling point loads in concourses and split-slab conditions on the upper decks, the scope of performance expectations was extraordinary.
With design by HOK (360 Architecture), architectural detailing by Ewing Cole, and structural engineering by Thornton Tomasetti, all working under a design-build arrangement with SKANSKA USA, bridging and sealing these large (10-inch nominal) seismic expansion joints fell to Emseal and installer Schnell Contracting Services.
It’s hard to believe that 8+ years have passed since installation began of the 4,200 LF of SJS System and SJS-FP expansion joints in the 83,000 seat, 1.6 billion dollar new Meadowlands Metlife stadium. With stainless-steel coverplates throughout—on the concourses, treads, and even on the risers—the Jets/Giants really did it right.
Even close up, the SJS System is unobtrusive and the long-bevel, flint-blasted coverplates provide an accommodating walking surface.
Here’s how it went down…
…the epoxy-and-sand-coated blockouts were primed using Emprime.
Using a non-sag additive and Emcrete elastomeric nosing material, the blockouts were trowell-filled in the risers, and…
For the mockup, as for the entire project, each tread and riser section of SJS System was custom-fabricated to field measurements made by the contractor. Each piece was labeled and staged adjacent to its place in the bowl. Each piece comes precompressed to less than the joint size and with pre-attached hanger bars to aide installation.
The process is repeated to install all the interlocking tread/riser, foam/spline, custom-90 assemblies of the SJS System.