EMSEAL is committed to making custom-assembled orders fast. We share with you the goal of getting the right product, in the right size, to the project in a timeframe to meet the construction schedule.

This information is updated every day we are open at mid-day and is the same as our Tech Team will give you on the phone.

Lead time estimates are business days to manufacturer only, ex-factory, after receipt of a purchase order and all information enabling work to proceed. The most efficient and effective way to provide most of this information is on The EMSEAL Checklist.

Send us your PO now and we can provide a firmer lead time quote when it is entered.  Otherwise, these estimates can be affected by what is on the shop floor on any given day.
 
Product: Current Manufacturing
Lead Time Estimate :
Notifications:
One coat products:


 

 

 

 

 

 

 

 

 All times are ex-factory manufacturing times and do not include transit time for shipping.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COLORSEAL 5-6 business days
COLORSEAL-ON-A-REEL
DSM SYSTEM
HORIZONTAL COLORSEAL
SEISMIC COLORSEAL
Infrastructure: BEJS
SubmerSeal 7-8 business days
Two coat products:
DSM-DS 6-7 business days
EMSHIELD DFR2 or DFR3
QuietJoint SHH
SEISMIC COLORSEAL DS
SecuritySeal SSF2 or SSF3
Multi coat products:
EMSHIELD WFR2 or WFR3 7-8 business days
QuietJoint SHG
SecuritySeal SSW2
Uncoated foam products:
BACKERSEAL 5-6 business days
20H SYSTEM
25V
Specialty-OEM:
AST

6 business days

MST
Log Home - Classic or Acrylic
 
SJS SYSTEM  
SJS Quick-Ship: EMSEAL has implemented a stocking program for popular sizes of SJS SYSTEM.  We now stock material for 4, 5, 6, 7, & 8" SJS with standard 3/8" thick aluminum coverplates.  Orders of straight runs of 200-LF or less of these sizes with standard deck-deck coverplates will usually ship within: 7 business days
For non-stock sizes, stainless plates, deck-to-wall plates or other custom configurations, lead times will vary but usually will range from: 2-3 weeks
 
SJS-FR1 or SJS-FR2 2-3 weeks
 
FP (For Plaza) products:
MIGUTAN FP 2-3 weeks
SJS-FP
SJS-FP-FR
DSM-FP
DFR-FP
 
Winged parking garage seals:
THERMAFLEX TM and TCR
straight runs with or without end terminations 2-4 business days
with multiple direction changes 5-6 days
 
RoofJoint TPO or NPVC
straight runs with or without end terminations 2-4 business days
with multiple direction changes 5-6 business days
 
BG SYSTEM
straight runs with or without end terminations 2-4 business days
with multiple direction changes 5-6 business days
 
Interior wall and floor:
MIGUTRANS FS Series, FN/FTN SURFACE MOUNTED, KF 55, KF 250, etc.
In-stock items and quantities 2-3 business days
Special order items and quantities 2-3 weeks

Rev.10/24/2014 

 
Truckload of EMSEAL For Indianapolis Colts Lucas Oil Stadium Please note: On orders for a large quantity of  sticks (100+ sticks) or orders with a lot of factory-welds and transitions, lead times may be longer than average. 

Please plan accordingly or call
1-800-526-8365 (508-836-0280) for a specific quote.

 


EMSEAL JOINT SYSTEMS LTD. 25 Bridle Lane, Westborough, MA 01581
EMSEAL LLC. 120 Carrier Drive, Toronto, ON M9W 5R1

   

 


1-800-526-8365 -- 508-836-0280 --  techinfo@emseal.com -- Fax: 508-836-0281

Last Modified: October 24, 2014

Copyright © 1998-2014 by EMSEAL Joint Systems, Ltd. All rights reserved.
This document may not be reproduced in whole or in part without permission.