Average Foam Sealants Lead Times History (actual days ex-factory)

  Coated Sticks UnCoated Sticks Reels
       
2011      
January 3.4 1.6 2.8
February 2.5 1.5 2.3
March 3.6 2.6 2.9
April 5.1 3.3 3.6
May 3.5 2.2 5.7
June 3.8 1.7 6.2
July 4.2 3.3 7.7
August 4.8 2.6 8.5
September 3.3 2.0 6.1
2010      
January 2.9 1.9 1.8
February 2.5 1.3 1.3
March 2.6 1.4 1.9
April 2.9 2.1 2.1
May 3.3 2.7 3.5
June 3.4 3.2 3.6
July 3.7 3.0 3.8
August 4.4 3.2 3.9
September 3.0 3.1 3.5
October 3.9 3.6 3.1
November 2.9 2.1 2.0
December 3.0 2.0 2.0
2009      
January 2.3 1.7 1.7
February 2.8 1.7 1.5
March 2.6 1.9 1.8
April 2.1 1.5 1.5
May 2.9 1.8 2.5
June 3.5 2.3 2.5
July 4.8 4.0 3.0
August 4.6 4.0 3.9
September 2.5 1.7 3.1
October 2.4 2.3 3.0
November 2.1 1.8 2.3
December 3.1 1.8 1.7
2008      
January 3.3 1.9 2.5
February 3.0 1.7 2.4
March 3.0 1.8 3.4
April 3.1 2.0 2.5
May 2.9 2.0 3.5
June 3.0 3.0 2.2
July 2.6 1.8 1.9
August 2.5 1.8 2.3
September 2.0 1.8 2.0
October 1.8 1.6 2.0
November 1.9 1.5 1.5
December 1.5 1.0 1.0

Glossary:
Coated Sticks: COLORSEAL, SEISMIC COLORSEAL, DSM SYSTEM, HORIZONTAL COLORSEAL, DSH SYSTEM

UnCoated Sticks: 20H SYSTEM, 25V, BACKERSEAL (1 1/4" (30mm) and larger).

Reels: BACKERSEAL, 25V (1" (25mm) and smaller).

EMSEAL is committed to making custom-assembled orders fast.  Our goal is to ensure that the right product, in the right size, gets to the project in a timeframe that is in sync. with the construction schedule:

Average lead times:

All foam products* are averaging 4.5 business days ex-factory after receipt of all information enabling work to proceed.
These include: COLORSEAL, SEISMIC COLORSEAL, DSM SYSTEM, HORIZONTAL COLORSEAL, BACKERSEAL, DSH SYSTEM, 20H SYSTEM, and 25V

EMSHIELD DFR2 which is a fire-rated, watertight, trafficable system is running 7.0 business days ex-factory after receipt of all information enabling work to proceed. The New EMSHIELD WFR2 fire-rated, watertight, energy-efficient system is running 6.0 business days ex-factory.
 
Truckload of EMSEAL For Indianapolis Colts Lucas Oil Stadium Please note: On single orders for a large quantity of  sticks (100+ sticks) lead times may be longer than average.  Please plan accordingly or call
1-800-526-8365 (508-836-0280) for a specific quote).


*double-sided coated products SEISMIC COLORSEAL DS, COLORSEAL-DS, DSM-DS, are running about 2 additional business days ex-factory and custom colors as short as one week and up to two-weeks.

Parking and plaza deck and in-stock Interior Floor products
EMSEAL's production schedules have been averaging
3 business days ex-factory and depends on the model, quantity, number of factory-fabricated transitions on the order and on the receipt of all information including approved fabrication drawings as necessary.
These include: THERMAFLEX, MIGUTAN, MIGUTRANS, FN/FTN SURFACE MOUNTED, BG SYSTEM

SJS SYSTEM is running about 2-3 weeks (check with us).

 


Meet online now:

Expansion joints and precompressed joint sealants by EMSEAL

1-800-526-8365 -- 508-836-0280 --  techinfo@emseal.com -- Fax: 508-836-0281

EMSEAL JOINT SYSTEMS LTD. 25 Bridle Lane, Westborough, MA 01581
EMSEAL LLC. 120 Carrier Drive, Toronto, ON M9W 5R1

Last Modified: February 01, 2012



Copyright © 1998-2012 by EMSEAL Joint Systems, Ltd. All rights reserved.
This document may not be reproduced in whole or in part without permission.