8:00am
Joint size and temperature compared to ensure proper sized joint material on site.
BEJS material stored in shade to increase working time on hot day.
Failed rubber seal removed and joint faces sandblasted to white metal.
10:00am
Checking the expansion rate of a small piece of BEJS foam to determine working time.
Mixing the BEJS epoxy adhesive.
Troweling the BEJS epoxy onto the joint face.
10:30am
Unwrapping the BEJS and removing it from its hardboard and shrink-wrap packaging.
Inserting BEJS into wet epoxy on joint faces. Set to 1/2″ from top of metal angles.
Applying the joining silicone to seal the butt joins and inserting remaining sticks of BEJS material.
10:45am
Cleaning the silicone top surface with solvent to remove excess epoxy.
Injecting and tooling silicone sealant bands between the bellows and the epoxy-coated joint face.
11:00am
Removing duct tape from top of metal angles.
Complete BEJS joint installation.